Verify mobile number to view the solution
Solutions
Given:
Time taken by A to complete \(20 \%\) work \(=4\) days
Time taken by \(B\) to complete \(33.33 \%\) of work \(=10\) days
They worked together for 9 days
C completed the remaining work in 6 days
As we know,
Work \(=\) Time \(\times\) Efficiency
Time taken by A to complete \(100 \%\) work \(=4 \times 5=20\) days
Time taken by B to complete \(100 \%\) work \(=10 \times 3=30\) days
L.C.M of 20 and \(30=60=\) Total work
Efficiency of \(A=\frac{60}{20}\)
\(=3\) units/day
Efficiency of \(B=\frac{60}{30}\)
\(=2\) units/day
Worked done by \(A\) and \(B\) together in 9 days \(=(3+2) \times 9\) \(=45\) units
Remaining work \(=(60-45)\) units
\(=15\) units
C can complete the remaining work in 6 days
Efficiency of \(C=\frac{15}{6}=2.5\) units/day
Total efficiency of \(B\) and \(C=(2+2.5)\) units/day
\(=4.5\) units / day
Now, \(75 \%\) of total work \(=75 \%\) of 60 units
\(=45\) units
Required time \(=\frac{45}{4.5}\) days
\(=10\) days
\(\therefore B\) and \(C\) can complete \(75 \%\) work in 10 days.
Hence, the correct answer is 10.