Given:
A can do work in days = 15
The efficiency of B = Efficiency of A - 10%
The efficiency of C = Efficiency of A + 20%
Work done by A, B and C = 3 days

Formula Used:
Total work = Efficiency × Days
Calculation:

Let's assume that the efficiency of A is 100 units per day
So,
Efficiency of B = 100 -10% of 100 = 90 units per day
Efficiency of C = 100 + 20% of 100 = 120 units per day
⇒ Work done by A + B + C in a day = 100 + 90 + 120 = 310 units
⇒ Total work = Work done by A in a day × Days
⇒ Total work = 100 × 15 = 1500 units
⇒ Work done by A+ B + C = 310 × 3 = 930 units
⇒ Remaining work = 1500 - 930 = 570 units
⇒ 570 units of work done by D in days = 19/2
⇒ 1500 units of work will be done by D in days

∴ D will complete work in 25 days.