Verify mobile number to view the solution
Solutions
Let the total amount of work be 360 units (LCM of 40 and 18)
Let the work done by Mayukh per day be x and that by Sharan be y.
⇒ Work done by Mayukh and Sharan together in one day = x + y = 360/18 = 20 units.
⇒ Time is taken by Mayukh to complete 1/3rd of work = 120/x
⇒ Time is taken by Sharan to complete remaining work = 240/y
the duo could complete the task in 40 days,
⇒ 120/x + 240/y = 40
⇒ 120/ (20 – y) + 240/y = 40
⇒ 120y + 240(20 – y) = 40y(20 – y)
⇒ 3y + 120 – 6y = 20y – y2
⇒ y2 – 23y + 120 = 0
⇒ (y – 15)(y – 8) = 0
⇒ y = 8 (Work done per day by Sharan will be lesser than Mayukh)
∴ Time required by Sharan alone = 360/8 = 45 days.
Shortcut Trick
Option method:-
Sharan and Mayukh, working together, can complete a task in 18 days
if both have the same efficiency Sharan and Mayukh are alone in the work for 36 days.
now, as per the question condition,
Mayukh worked faster than Sharan
It means the time required by Sharan alone must be 36 + days and
(In this condition our 2 options are eliminated 24,30)
2nd thing it can't be double either.
In this condition, we are left with only one option (1 ) 45 Days