Correct Answer: It is measured as per drawing stating thickness. The description must include framework, finishing, curing, etc.
Explanation:
For Damp Proof Course (DPC) in civil engineering measurement:
DPC is measured in square meters (m²) with specified thickness mentioned in the description.
The description also includes details like formwork (if any), finishing, curing, and method of application.
Why others are incorrect:
-
Not measured in cubic meter → DPC is not a volume item.
-
Does not include grouting → Grouting is a separate item.
-
Volume of material is not measured → Only area with thickness is considered.
So, the true statement is:
It is measured as per drawing stating thickness. The description must include framework, finishing, curing, etc.