Please wait...

RCC Design Test 4
Menu grid icon
Result Result point icon
RCC Design Test 4
  • Goals icon

    /

    Score
  • Trophy icon

    -

    Rank
White alarm icon Time Taken: -
Result frame illustration
  • Question 1/10
    1 / -0

    As per IS code, the minimum grade of concrete for the design of prestressed concrete structure is:-
    Solutions

    Minimum grade of concrete to be used in the design of prestressed concrete structure as per IS 1343 is as below:

    1. For Post tensioning minimum grade of concrete used is M-30.

    2. For Pre-tensioning minimum grade of concrete used is M-40.

    Cover to be used in the design of prestressed concrete structure as per IS 1343 is as below:

    1. For Posttensioning minimum cover to be used is 30 mm.

    2. For Pre-tensioning minimum cover to be used is 20 mm.
  • Question 2/10
    1 / -0

    The elastic shortening loss in a post-tensioned beam when all the wires are stressed simultaneously if the stress developed in concrete at the level of prestressing cable is 10 MPa and the modular ratio is given as 6.
    Solutions

    Concept:

    Post-Tensioned member: If all the cables are stressed simultaneously and anchored then there will not by any elastic shortening loss because the recording of prestress is done just before anchoring and cables are stretched by taking reaction from the concrete number. Hence at the time of recording of prestress, elastic shortening in concrete would have already occurred.

    Hence there will be no loss in stress in the post-tensioned member when all the wires are stretched simultaneously.

    Important Point:

    Elastic shortening loss:

    • Pre-tensioning member: When cables are stretched prestressing force is transferred to the member and concrete undergoes immediate elastic shortening due to the prestressed force. Due to the bond between steel and concrete, elastic shortening will also occur in steel leading to strain loss. Strain loss leads to stress loss.
  • Question 3/10
    1 / -0

    As per IS 1343, The minimum clear spacing in case of single wires used in pre-tensioning system shall not be less than:
    Solutions

    As per clause 11.1.7.1 of IS 1343,

    In case of single wires used in pre-tensioning system, the minimum clear spacing shall not be lesser than greater of the following:

    1) 3 times the diameter of wire, and

    2) \(1\frac{1}{3}\) times the maximum size of aggregate.

  • Question 4/10
    1 / -0

    A post-tensioned beam of 8 m span is prestressed with a parabolic tendon of 9 m length. While transferring the prestress three was an anchorage slip of 9 mm. The loss of stress in the cable due to anchorage slip (in MPa up to 2 decimal places) is _______. (consider E = 2 × 105 MPa for the tendon)
    Solutions

    Concept:

    Loss due to anchorage slip:

    •  In a post-tensioned member in which prestress is transferred through concrete, the anchorage slip loss occurs before the tendon wedge assembly is properly sealed. The anchor slip reads to reduction in the strain in the cable (εs)

              Stress loss in cable due to anchorage slip = εs Es

              Also, \({\varepsilon _s} = \frac{{{\rm{\Delta }}\ell }}{\ell }\)                     

    where, Δℓ = Anchorage slip

    Calculation:

    ℓ = 9m = 9000 mm, Δℓ = 9 mm

    \(\therefore {\varepsilon _s} = \frac{{{\rm{\Delta }}\ell }}{\ell } = \frac{9}{{9000}} = \frac{1}{{1000}}\)

    Stress loss in the cable due to anchorage slip = εs Es \(= \frac{1}{{1000}} \times 2 \times {10^5}\) = 200 MPa    

    Important Point:

    Note that there is no loss due to anchorage slip in a pre-tensioned beam.

     

     

    Pre-tensioning

     

    Post-Tensioning

    1.

    Electric shortening loss

    1.

    No elastic shortening loss in cables if pulled simultaneously, however, losses will be there if cables are pulled are by one.

    2.

    Creep loss

    2.

    Friction loss

    3.

    Shrinkage loss

    3.

    Anchor slip loss

    4.

    Relaxation loss

    4.

    Creep loss

     

     

    5.

    Shrinkage & Relaxation

  • Question 5/10
    1 / -0

    An 8-meter-long simply supported beam of size 300 × 600 mm is prestressed with force of 1400 kN as shown in the figure below.

    Calculate the minimum eccentrically required at the mid span, so as to achieve complete load balancing of the beam loaded with uniformly described intensity of 30 kN/m (including self-weight).

    Solutions

    Since the applied load is uniformly distributed the tendon will follows parabolic profile for complete load balancing as shown below.

    For complete load balancing

    Intensity of applied U.D.L. = Intensity of U.D.L. produced by eccentric prestressing

    \(\therefore w = \frac{{8P \times e}}{{{L^2}}}\)

    \(\therefore 30 = \frac{{8 \times 1400 \times e}}{{{8^2}}}\)

    ∴ e = 0.17143 m = 171.43 mm.

  • Question 6/10
    1 / -0

    In a pretensioned beam of rectangular cross-section 150 mm × 300 mm is prestressed by 4 wires of 5 mm diameter each. The stress in the wire is 1200 MPa and the eccentricity provided is 50 mm from the soffit of the beam. The stress developed at the soffit of the beam considering the nominal concrete section is
    Solutions

    Calculation:

    When load is placed eccentrically, the stress is calculated as:

    Thus the stress distribution is

     

    e = 150 – 50 = 100 mm

    \(P = Stress \times Area = 1200 \times \left( {4 \times \frac{\pi }{4} \times {5^2}} \right)\) = 94.25 kN

    \(\therefore {\sigma _A} = \frac{P}{A} + \frac{{Pe}}{Z} = \frac{{94.25 \times {{10}^3}}}{{150 \times 300}} + \frac{{94.25 \times {{10}^3} \times 100}}{{\left( {\frac{{150 \times {{300}^2}}}{6}} \right)}}\) = 6.28 MPa

  • Question 7/10
    1 / -0

    A post tensioned beam 150 mm × 350 mm is prestressed by a parabolic cable with an eccentricity of 50 mm above the centroid at the supports and an eccentricity of 75 mm below the centroid at mid span. Area of cable is 500 mm2 and initial prestress is 1000 MPa. Wobbling constant is 0.0015/m, coefficient of friction is 0.55. The percentage of loss of prestress due to friction over 10 m span of beam, if jacking is done from one end is ___
    Solutions

    Concept:

    Loss due to friction = Px – P0

    PX = Po [1 – (μα + kx)]

    Where

    Px = Initial prestress

    Po = stress in wire while jacking

    μ = coefficient of friction

    k = wobbling constant

    α = cumulative angle of inclination for prestress bar

    x = distance for a particular section of the beam taken from face end

    Calculation:

    Given:

    Coefficient of friction (μ) = 0.55

    Friction coefficient of wave effect = 0.0015/m

    \({\rm{Slope\;of\;angle\;}} = \left( {\frac{{4{\rm{e}}}}{{\rm{L}}}} \right) = \left( {\frac{{4\left( {50 + 75} \right)}}{{10 \times {{10}^3}}}} \right) = 0.05\)

    Cumulative angle (α) = 2 × 0.05 = 0.1

    Po = stress in wires at jacking end

    Px = 1000 MPa

    ∴ Px = Po [1 – (μα + kx)]

    1000 = Po [1 – (0.55 × 0.1 + 0.0015 × 10)]

    \(\therefore {{\rm{P}}_{\rm{o}}} = \frac{{1000}}{{0.93}} = 1075.268{\rm{\;MPa}}\)

    Loss of stress in cable = 1075.268 – 1000 = 75.268 MPa

    ∴ Percentage loss of prestress \(= \frac{{75.268}}{{1075.268}} \times 100 = 7\%\)
  • Question 8/10
    1 / -0

    A simply supported prestressed beam having a cross-section of 250 mm × 400 mm and loaded as shown below.

    The minimum eccentricity such that a prestressing force of 400 kN lead to no tension at the soffit of the beam is (in mm up to 2 decimal places)

    Solutions

    Concept:

    The unit weight of PCC is 24 kN/m.

    Under the limiting condition for no tension at the soffit of the beam, the stress should be zero.

    Calculation:

     

    Dead load = 24 × 0.4 × 0.25 × 1 = 2.4 kN/m

    Total load = L.L + D.L = 2.4 + 4 = 6.4 kN/m

    The maximum moment in a simply supported beam occurs at the mid-span and it is given as \(\frac{{\omega {\ell ^2}}}{8}\)

    M at mid-span \(= \frac{{\omega {\ell ^2}}}{8} = \frac{{6.4\; \times \;{8^2}}}{8} = 51.2\;kN - m\)

    Let the eccentricity be e.

    For no tension at base, σA = 0

    \(\Rightarrow {\sigma _A} = \frac{P}{A} + \frac{{Pe}}{z} - \frac{M}{z} = 0\)

    \(\Rightarrow \frac{{400\; \times \;{{10}^3}}}{{250\; \times \;400}} + \frac{{400\; \times \;{{10}^3}\; \times \;e}}{{\left( {\frac{{250\; \times\; {{400}^2}}}{6}} \right)}} - \frac{{51.2\; \times\; {{10}^6}}}{{\left( {\frac{{250\; \times \;{{400}^2}}}{6}} \right)}} = 0\)   e = 61.33 mm

    Mistake point:

    In prestress, the design is done using the working stress method, and hence factored load is not considered.

  • Question 9/10
    1 / -0

    A 7m long simply supported beam is prestressed as shown in figure below.

    If the effective flexural rigidity EI = 2 × 104 kN - m2. The total loss of prestressing force is 11% and the initial prestressing force is 240 kN, then the net increase in the length of the prestressing cable is ______ mm (up to two decimal places). Neglect the effect due to dead load.

    Solutions

    Effective Prestressing force = (1 - 0.11) × 240

    P = Peff = 213.6 kN

    Span = 7m

    EI = 2 × 104 kN - m2

    Slope of beam due to UDL:

    \({\theta _1} = \frac{{w{L^3}}}{{24EI}}\)

    \({\theta _1} = \frac{{8 \times {{\left( {7000} \right)}^3}}}{{24 \times 2 \times {{10}^{13}}}} = 5.7 \times {10^{ - 3}}\;\left( {down\;wood} \right)\)

    Slope of beam due to Prestressing force:

    Using area moment method

    \({\theta _2} - {\theta _C} = \frac{{Pe}}{{EI}} \times \frac{L}{2}\)

    θC = 0

    \({\theta _2} = \frac{{ 213.6 \times {{10}^3} \times 75 \times 7000}}{{2 \times {{10}^4} \times {{10}^9} \times 2}} = 2.80 \times {10^{ - 3}}\)

    Net slope of the beam = θ1 - θ2

    θnet = 5.7 × 10-3 – [2.80 × 10-3]

    θnet = 2.9 × 10-3

    Now,

    Total increase in length = 2eθ

    = 2 × 75 × 2.9 × 10-3

    = 0.435 mm

  • Question 10/10
    1 / -0

    A post tensioned member of rectangular cross-section 150 mm wide and 300 mm depth is stressed by a parabolic cable profile. The eccentricity at the supports is zero and that at the center is 60 mm. If the area of cable is 50 mm2 and stress induced is 1400 MPa, then the loss in stress due to creep is (in mm up to 2 decimal places)_____

    (Consider m = 6 , Ultimate creep coefficient = 1.6)

    Solutions

    Concept:

    Loss in prestress due to creep:

    Creep loss = Ultimate creep strain × Es

    Ultimate creep coefficient (θ) \(= \frac{{Ultimate\;creep\;strain}}{{Elastic\;strain}}\)

    Ultimate creep strain = Elastic strain × θ

    Also, Elastic strain \(= \frac{{{f_c}}}{{{E_c}}}\)

    \(\therefore Creep\;loss = \frac{{{f_c}}}{{{E_c}}} × \theta × {E_s}\) = m × fc × θ

    Where,  fc is the stress in concrete at the level of prestressing cable.

    Generally, the fc calculated shall be the value of fc after deducting the initial losses or short term losses. Creep losses are around 2 – 3% of the initial prestress.

    \({f_{CA}} = \frac{P}{A}\;\;\;;\;\;{f_{CB}} = \frac{P}{A} + \frac{{P{e^2}}}{I}\)

    \({f_{Cavg}} = \frac{{{f_{CA}} × \frac{\ell }{2} + \frac{2}{3} × \frac{\ell }{2}\left( {{f_{CB}} - {f_{CA}}} \right)}}{{\frac{\ell }{2}}}\)

    \(\Rightarrow {f_{Cavg}} = {f_{CA}} + \frac{2}{3}\left( {{f_{CB}} - {f_{CA}}} \right)\)

    Calculation:

    P = 1400 × 50 = 70 kN, b = 150 mm, d = 300 mm

    Stress in concrete at the support \(A = {f_{CA}} = \frac{P}{A} = \frac{{\left( {1400\; × \;50} \right)}}{{150\; × \;300}} = 1.56\;MPa\)

    Stress at the mid-span at B \(= {f_{CB}} = \frac{P}{A} + \frac{{P{e^2}}}{I}\) = \(\frac{{\left( {1400\; × \;50} \right)}}{{150\; × \;300}} + \frac{{1400\; × \;50\; × \;{{60}^2}\; × \;12}}{{150\; × \;{{300}^3}}}\) = 2.302 Mpa

    \({f_{cavg}} = {f_{CA}} + \frac{2}{3}\left( {{f_{CB}} - {f_{CA}}} \right) = 1.56 + \frac{2}{3}\left( {2.302 - 1.56} \right)\) = 2.055 MPa

    Loss due to creep = m × fcAvg × θ = 6 × 2.055 × 1.6 = 19.728 MPa

Close button icon
User Profile
-

Correct (-)

Wrong (-)

Skipped (-)


  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
Mockers logo Get latest Exam Updates
& Study Material Alerts!
No, Thanks
Arrow pointer icon
Click on Allow to receive notifications
Notification bell icon ×
Open Now